Nichapie
Dam Stalled

Itare Dam

Kericho Rift Valley Kenya

Proposed dam in Kericho County to supply water to Nakuru town, stalled due to procurement and financing issues.

AnnouncedJanuary 1, 2017

Financials

Offering PriceKsh 28,000,000,000KES

Timeline

Project Announced

January 1, 2017

Itare Dam announced as a key water supply project for Nakuru

Project Stalled

January 1, 2019

Project stalled due to contractor issues and procurement controversies

Contractors

CMC di Ravenna / Itinera S.p.A.

Initially Contracted (Terminated)
Ksh 28,000,000,000 Italy

Same Italian consortium as Arror/Kimwarer; contract terminated due to performance issues

Politicians Involved

Henry Rotich

Cabinet Secretary for the National Treasury
Jubilee Party

Oversaw financing arrangements for the dam project

Benefits

Water supply for Nakuru city, improved sanitation, support for urban growth

Description

The Itare Dam was planned to be constructed on the Itare River in Kericho County to supply treated water to Nakuru town and surrounding areas. The project has been stalled due to procurement controversies, financing challenges, and disputes with the initial contractor. It was intended to address severe water shortages in Nakuru, one of Kenya's fastest-growing cities.

Overview

Critical water supply project for Nakuru city, which faces chronic water shortages despite its rapid urbanization and designation as a city.

Sources

damitarekerichonakuruwater-supplystalled