Nichapie
Dam Stalled

Koru-Soin Multipurpose Dam

Kisumu Nyanza Kenya

KSh 19.9 billion multipurpose dam on River Nyando for flood control, water supply, irrigation, and 2.5MW hydropower generation. Stalled due to funding issues.

AnnouncedJanuary 1, 2009
StartedAugust 27, 2022
Expected CompletionAugust 27, 2027

Financials

Offering PriceKsh 19,900,000,000KES

Timeline

Project Conceptualized

January 1, 1993

Koru-Soin Dam first conceptualized as flood control measure for Nyando plains

Feasibility Study Completed

June 1, 2020

National Water Harvesting and Storage Authority completed designs and feasibility study

Contract Awarded

May 11, 2022

Tender awarded to China Jiangxi joint venture at KSh 19.9 billion

Construction Commenced

August 27, 2022

Contractor received KSh 499 million advance payment and began mobilization

Contractor Suspends Work

Scandals & Controversies
September 1, 2023

China Jiangxi suspended operations citing non-payment, demanding KSh 846.5 million. Government had allocated only KSh 100 million against KSh 3 billion budget

PPP Financing Explored

April 1, 2025

Government announced shift to PPP model after the 100% government funding approach proved untenable

Scandals & Controversies

Contractor Suspends Work

September 1, 2023

China Jiangxi suspended operations citing non-payment, demanding KSh 846.5 million. Government had allocated only KSh 100 million against KSh 3 billion budget

Contractors

China Jiangxi International Kenya Limited & China Jiangxi International Economic and Cooperation Co. Ltd.

Main Contractor (Joint Venture)
Ksh 19,900,000,000 China

Chinese joint venture awarded the contract on May 11, 2022 after quoting KSh 20 billion—33% less than government estimate

Politicians Involved

William Ruto

President
UDA

Government exploring PPP arrangement under his administration to complete the stalled project

Eliud Owalo

Deputy Chief of Staff
UDA

Leading discussions with private sector investors for PPP financing model

Zachariah Njeru

Cabinet Secretary for Water and Irrigation
Independent

Assured the public of government commitment to complete the dam and boost rice production

Benefits

Flood control, domestic water supply, irrigation of 2570 hectares, 2.5MW hydropower, reduced pumping costs at Ahero Irrigation Scheme

Description

The Koru-Soin Multipurpose Dam is a major infrastructure project straddling Kisumu and Kericho counties on River Nyando, approximately 5km upstream of Muhoroni town. Originally conceptualized in the early 1990s and formally launched in 2009, the dam is designed as a zoned rock-fill structure with 93.7 million cubic metres storage capacity. It will supply 72,000m³/day of domestic water, irrigate 2,570 hectares, and generate 2.5MW of hydropower. The KSh 19.9 billion contract was awarded to China Jiangxi International Kenya Limited and China Jiangxi International Economic and Cooperation Co. Ltd. on May 11, 2022. The contractor received KSh 499 million advance payment but suspended operations in September 2023 citing non-payment, demanding an additional KSh 846.5 million. The government allocated only KSh 100 million against a KSh 3 billion budget in FY 2022-2023. As of 2025, the government is exploring PPP arrangements to complete the project.

Overview

Critical for controlling the devastating perennial flooding in Nyando plains that displaces over 40,000 people, while providing water, irrigation, and power to Kisumu and Kericho counties. The dam would decommission expensive electric pumps at Ahero Irrigation Scheme, benefiting over 30,000 farmers.

Sources

infrastructuredamkisumukerichowestern-kenyaflood-controlnyanza