Nichapie
Bridge Operational

Liwatoni Floating Bridge (Mombasa)

Mombasa Coast Kenya

660m floating pedestrian bridge across the Likoni Channel providing alternative crossing to the Likoni Ferry for foot traffic.

AnnouncedMay 1, 2020
StartedJune 1, 2020
Expected CompletionDecember 31, 2020
CompletedNovember 1, 2020

Financials

Offering PriceKsh 1,500,000,000KES
Actual CostKsh 1,500,000,000KES
Cost Variance Ksh 0 0.0%

Timeline

Rapid Construction

June 1, 2020

Construction began during COVID-19 pandemic to reduce Likoni Ferry overcrowding

Bridge Opened

November 1, 2020

Liwatoni Floating Bridge opened to pedestrians

Contractors

China Road and Bridge Corporation (CRBC)

Main Contractor
Ksh 1,500,000,000 China

Built the floating pedestrian bridge within 6 months

Politicians Involved

Uhuru Kenyatta

President of Kenya
Jubilee Party

Commissioned the floating bridge as an interim Likoni crossing solution

Benefits

Pedestrian crossing alternative, reduced Likoni Ferry congestion, COVID-19 social distancing compliance

Description

The Liwatoni Floating Bridge is a 660-metre pedestrian floating bridge across the Likoni Channel in Mombasa, built by China Road and Bridge Corporation at a cost of KES 1.5 billion. Constructed as an interim solution to complement the Likoni Ferry while the Mombasa Gate Bridge is being planned, it provides a walking crossing for pedestrians between Mombasa Island and the South Coast mainland. The bridge was built rapidly in response to overcrowding on the Likoni Ferry, especially during COVID-19 pandemic social distancing requirements.

Overview

First fixed crossing between Mombasa Island and South Coast mainland, providing pedestrian relief from the overcrowded Likoni Ferry service.

bridgemombasalikonifloating-bridgepedestrianchinese-fundedcovid-19