Nyansiongo-Manga-Ikonge Road

Nyamira Nyanza Kenya

Construction of the 22km Nyansiongo-Manga-Ikonge road to bitumen standard in Nyamira County.

AnnouncedJanuary 1, 2014
StartedMarch 1, 2015
Expected CompletionDecember 31, 2018
CompletedJune 1, 2019

Financials

Offering PriceKsh 850,000,000KES
Actual CostKsh 850,000,000KES
Cost Variance Ksh 0 0.0%

Timeline

Construction Commenced

March 1, 2015

Road upgrading works began from Nyansiongo end

Road Completed

June 1, 2019

Full bitumen surfacing completed and road opened to traffic

Contractors

Sino Hydro Corporation

Main Contractor
Ksh 850,000,000 China

Chinese engineering firm for road construction

Politicians Involved

John Nyagarama

Governor
ODM

Championed road construction for tea farming zones

Benefits

Improved tea transport, all-weather road access, reduced travel time, economic growth

Description

The Nyansiongo-Manga-Ikonge road project involved upgrading a 22km stretch from Nyansiongo through Manga to Ikonge from murram to bitumen standard. The road traverses key tea-growing zones in Nyamira County and connects several trading centres. Previously, the road was impassable during rainy seasons, isolating farming communities and causing significant post-harvest losses for tea and pyrethrum farmers. The project was funded through the Kenya Rural Roads Authority and included proper drainage, culverts, and road markings.

Overview

Opened up productive tea farming areas in Nyamira's highlands, significantly reducing post-harvest losses