Vihiga County Headquarters and Offices

Vihiga Western Kenya

Construction of Vihiga County government headquarters and office complex in Mbale town.

AnnouncedJanuary 1, 2014
StartedJanuary 1, 2015
Expected CompletionDecember 31, 2019
CompletedDecember 1, 2019

Financials

Offering PriceKsh 500,000,000KES
Actual CostKsh 500,000,000KES
Cost Variance Ksh 0 0.0%

Timeline

Construction Started

January 1, 2015

Groundbreaking for county headquarters complex

Headquarters Completed

December 1, 2019

County offices completed and occupied

Contractors

County Construction Firms

Main Contractor
Ksh 500,000,000 Kenya

Local construction firms handling headquarters construction

Politicians Involved

Moses Akaranga

First Governor
Amani National Congress

Initiated construction of permanent county headquarters

Benefits

Permanent county offices, improved governance, civic pride, reduced rental costs

Description

The Vihiga County Headquarters project involved construction of a modern government office complex in Mbale town to house county government departments, the county assembly, and related services. Since the creation of Vihiga County under devolution in 2013, the county government operated from temporary premises. The new headquarters includes executive offices, a county assembly chamber, departmental offices, and conference facilities. The project was funded through county development funds and aimed to provide a permanent administrative base for the county's governance structures.

Overview

Permanent administrative infrastructure for one of Kenya's smallest counties, enabling effective devolved governance