Vihiga-Kisumu Road (via Maseno) Rehabilitation

Vihiga Western Kenya

Rehabilitation of the 25km Vihiga-Maseno-Kisumu road connecting Vihiga County to Kisumu city.

AnnouncedJanuary 1, 2014
StartedJanuary 1, 2015
Expected CompletionDecember 31, 2018
CompletedMarch 1, 2019

Financials

Offering PriceKsh 1,500,000,000KES
Actual CostKsh 1,500,000,000KES
Cost Variance Ksh 0 0.0%

Timeline

Road Rehabilitation Started

January 1, 2015

Contractor mobilized for road works

Road Completed

March 1, 2019

Road rehabilitation completed and opened to traffic

Contractors

H Young and Company

Main Contractor
Ksh 1,500,000,000 Kenya

Kenyan road construction and civil engineering company

Politicians Involved

Moses Akaranga

Governor
Amani National Congress

Supported road rehabilitation for county connectivity to Kisumu

Benefits

Improved Kisumu connectivity, commuter transport, university access, economic integration

Description

The Vihiga-Maseno-Kisumu road rehabilitation project covered the 25km stretch connecting Vihiga County through Maseno to Kisumu, western Kenya's largest city. The road passes through Maseno, home to Maseno University, one of Kenya's oldest academic institutions. The rehabilitation included resurfacing, drainage improvements, and installation of safety features. The road carries significant daily commuter traffic between the densely populated Vihiga County and Kisumu's commercial hub. It is part of the broader B1 road network connecting western Kenya to Lake Victoria.

Overview

Key corridor connecting Kenya's second-smallest county to the Lake Victoria region's largest city